How crusher liners, jaw plates and blow bars should be packed for sea freight: crate and pallet selection by part weight, rust prevention, lashing and weight distribution inside a container, and the marking and documents that prevent a claim.
Packing is the part of a wear parts order that nobody negotiates and everybody pays for when it goes wrong. A 2-tonne mantle that breaks loose inside a container does not just damage itself; it takes the rest of the shipment with it, and the claim usually lands on the party that specified the packing.
This is how we pack and load, and what to specify if you are buying from anyone else.
The packing decision follows the piece weight, not the order value.
| Single piece | Usual packing | What it protects against |
|---|---|---|
| Under 50 kg | Carton on pallet, strapped | Handling, moisture |
| 50-300 kg | Plywood crate, screwed, on skid | Impact, compression, pilferage |
| 300-1500 kg | Heavy crate with internal blocking, forklift pockets | Shifting inside the crate |
| Over 1500 kg | Cradle or open-top frame bolted to a steel base | The crate itself failing |
Above roughly 1.5 tonnes a wooden crate is the wrong answer: the crate becomes the weakest item in the chain and fails at a corner, releasing the load. A bolted steel-base cradle, or the part bolted directly to a flat-rack bed, is the correct solution.
Manganese and chrome steel castings are shipped with machined faces - seating faces, bolt holes, sometimes a ground surface. Those faces rust in a container crossing the tropics.
What works, in order of reliability:
Three rules:
Weight goes low and over the axles. Heavy castings at the container floor, centred over the bogie area. A heavy liner stacked at the door end loads the chassis unevenly and is the first thing to shift in heavy weather.
No metal-to-metal contact without dunnage. Two castings touching will abrade through any coating in a day of road transport, and a bright wear scar is where rust starts.
Lash to the container’s rated points, not to the floor rings only. Floor rings are for light restraint. Heavy castings need lashing to the side rails or through the container’s lashing rings, with the angle kept shallow - a steep lashing pulls the fitting out.
A 20 ft container carries roughly 28 cubic metres and around 21-28 tonnes of payload depending on the lane and the chassis. Crusher wear parts are dense: a 20 ft container of liners will usually hit the weight limit before the volume limit.
That changes the packing approach: you are optimising for weight distribution and for not wasting height, not for cubic utilisation. Which means:
Per crate: shipping marks, gross and net weight, part number, quantity, and the heat number if the buyer needs traceability per piece. Mark on two faces, and put the same marks on the packing list.
Documents that prevent claims: packing list with per-crate weights, photos of the loaded container before the doors close, and the inspection report reference for each heat. The photos are the cheapest insurance in the whole transaction - they settle “was it damaged in transit or on arrival” in one glance.
Add these five lines, and most packing disputes disappear:
Our own packing is specified per order against the receiving site’s handling equipment - if your yard has a 5-tonne forklift and no overhead crane, say so, because it changes the crate design. For part identification before you order, see how to read a crusher parts part number.
Trusted by customers in 30+ countries. Standard lead time 15-30 days.
High manganese steel Mn13, Mn13Cr2, Mn18Cr2 and Mn22Cr2, plus high chrome iron (Cr26) for fine crushing. We select the material based on your abrasive and impact conditions - send your working conditions for a recommendation.
Aftermarket parts fit Metso (HP, GP, C, NP series), Sandvik (CH, CS, H, S series), Symons 2FT-7FT, Terex Pegson, Kleemann, McCloskey, Shanbao, SBM, Telsmith, Minyu, Hazemag and more. Any model can be custom made by drawing or sample.
Yes. Send a drawing (PDF, DWG or CAD) or a used sample. We measure, draft and confirm all dimensions with you before production. OEM part numbers are welcome for reference.
Standard lead time is 15-30 days and samples ship in 7-15 days. MOQ is flexible - trial orders from 1 piece are accepted.
ISO 9001 certified factory (Kaixin Certification, CNAS-accredited; certificate valid through June 2028). Every shipment includes a Material Test Report (MTR) with chemical composition and mechanical properties.
Export-standard wooden crates with rust protection. Sea and air freight from Shanghai and Ningbo ports to worldwide destinations.
| Material | Initial Hardness | Best For |
|---|---|---|
| Mn13 (ASTM A128) | HB 200-230 | General crushing with medium impact |
| Mn13Cr2 | HB 210-240 | Standard jaw plates and cone liners |
| Mn18Cr2 | HB 220-250 | High-impact, abrasive feed |
| Mn22Cr2 | HB 230-260 | Severe impact, hard and large rock |
| High Chrome Cr26 | HRC 58-62 | Blow bars, fine crushing of abrasive material |
* High manganese steel work-hardens under impact to 500+ HB at the wearing surface, giving long life in hard-rock crushing.
Interested in this product? Fill out the form below and we'll respond within 24 hours.